CL-01 · Labour sheet · VAT 18%
Installation, written as a labour sheet.
The bands below are for ordinary access in our coast map. Equipment is a separate line unless a row says the figure is all-in. The written quote is the price.
What a standard install contains
- The indoor unit mounted, and the outdoor unit on a standard bracket or rubber feet.
- Up to 3 m of insulated copper pair.
- Up to 3 m of gravity drain.
- One core through block. Reinforced concrete is an adder.
- Commissioning by a certified technician.
| Item | ILS |
|---|---|
| High-wall, 1.0–1.5 HP trade band (about 2.6–3.5 kW nameplate) | ₪1,180–₪1,650 |
| High-wall, 2.0–2.5 HP trade band (about 5.2–6.5 kW nameplate) | ₪1,650–₪1,890 |
| Cassette, ceiling void already there, one unit | ₪2,200–₪3,500 |
| Multi-split, one outdoor and two high-wall indoors, each run up to 3 m | ₪3,400–₪5,900 |
| Each further indoor head on that multi, labour | ₪1,450–₪2,200 |
High-wall and cassette
A high-wall unit needs a clear wall and a path for the pipes. A cassette needs an existing void of at least 300 mm under the slab and a panel we can lift for the filter. We do not build the gypsum ceiling. If the finished ceiling would sit below about 2.5 m, we propose a high-wall unit instead.
Roof condenser
| Condition | ILS |
|---|---|
| Condenser carried to a flat roof by stair or lift | add ₪480–₪1,000 |
| No lift, and the unit is carried above the third storey | add ₪180–₪650 |
| Crane or spider lift, when there is no safe carry path | quoted, often ₪1,800–₪3,500 |
The crane figure is the hire ticket we see on short Gush Dan lifts. It is not inside the bracket price. We name it on the quote before the day.
Pipe, drain, core, removal
| Adder | ILS |
|---|---|
| Copper beyond 3 m, up to 2 HP | ₪142 / m |
| Copper beyond 3 m, 2.5 HP and multi | ₪177 / m |
| Drain hose beyond 3 m | ₪48 / m |
| Reinforced-concrete core | ₪295–₪355 |
| Remove an old split, up to 2 HP | ₪295 |
| Remove an old split, 2.5 HP and above | ₪355 |
Pipe length stays inside the length printed for that model. If the roof is farther than the model allows, we say so before any core is drilled. We do not core a protected-space wall (mamad). A facade that forbids an outdoor unit means the roof, and only with the building’s written permission.
Equipment, for budgeting
The model is named on the quote, from the distributor list current that week. These all-in bands are for planning. They include a standard labour install and a current inverter unit. They are not a shelf price.
| Package | ILS |
|---|---|
| One high-wall, 1.0–1.5 HP trade band | ₪3,200–₪5,800 |
| One high-wall, 2.0–2.5 HP trade band | ₪4,400–₪7,200 |
| Multi, one outdoor and two indoors | ₪9,000–₪18,000 |
We do not print an efficiency percentage. The nameplate and the maker’s data sheet travel with the quote.
Request a survey. The visit is not reserved until we confirm it.